Plant Logistics and Equipment Installation for a New Cell Factory
From the truck to the installation site. Using our own lifting equipment and protective coverings. We transported the battery formation equipment for a new cell factory, mechanically installed it, and protected the already completed sections of the building throughout the entire installation process.
Contribution
Equipment logistics all the way to the installation site
Formation
Battery Formation Equipment
Security Plan
Floor and dust protection provided
Lifting Technology
Cranes and lifting equipment provided
The Initial Situation
The battery formation equipment was scheduled to be delivered for a new cell factory. The equipment arrived in several shipments and had to be brought into areas of the building where construction was already complete. Coated floors, finished interiors, and adjacent areas with cleanliness requirements meant that the simple solution of bringing the equipment in through the shell of the building was no longer an option.
Formation equipment is heavy and, at the same time, delicate. Its weight and dimensions determine which route is even feasible and which lifting equipment can still be used at the installation site. Dust and debris from transport pose a risk not only to the equipment itself but also to the surrounding areas. If the route isn’t determined until the truck reaches the loading ramp, the truck is held up, and the next delivery is delayed as well.
What We Have Taken On
We were responsible for the logistics, delivery, and mechanical installation of the formation equipment.
- Equipment Logistics: From Delivery to Installation Site
- Delivery Planning with Routes, Load Estimates, and Time Slots
- Provision of Cranes and Lifting Equipment
- Machine Installation of Battery Formation Equipment
- Mechanical Installation and Alignment at the Installation Site
- Temporary floor and dust protection in the affected areas
- Removal of Protective Measures and Handover of the Sites
A single point of contact from delivery through to the installation of the system, including the areas where the equipment was transported.
Installation without damaging finished surfaces
Lifting equipment should be chosen based on the load, not on a standard
From unloading directly to assembly
What Made This Project Special
The critical issue with such installations rarely lies in the lifting itself. It lies in determining whether the route is stable, whether there is still enough space for the lifting technique at the destination, and what happens to the surfaces over which the equipment is transported. We clarified these points before the first delivery and then carried out the installation in the planned order.
Because logistics, lifting equipment, safety measures, and installation were all included in a single contract, the client did not have to coordinate between freight forwarders, crane operators, and installation companies. Any delays in delivery could be absorbed within the scope of our contract, rather than having to reschedule a chain of individual contracts.
Project Data
- Role: Service provider responsible for delivery and installation
- Scope: Plant logistics and equipment installation
- Equipment: Battery Formation Equipment
- Lifting Technology: Cranes and Lifting Equipment Provided by GIGA
- Protection: Temporary floor and dust protection, including dismantling
- Installation: Mechanical Installation and Alignment
- Completion: Handover of the equipment to the subsequent trades