The Right Equipment for Heavy Loads
The new equipment has been delivered on time, the installation team is ready to go, and then it becomes apparent at the warehouse door that the clearance height isn’t sufficient or that the forklift can’t safely lift the load. When bringing machinery into a facility, just a few centimeters or metric tons can often make the difference between a project staying on schedule and falling behind. The cause rarely lies with the equipment itself, but rather with a decision made too late or based on incomplete data.
The right equipment depends on the load, the ground conditions, and the route to the installation site. This article explains what information you need before planning, where loading cranes, forklifts, air cushions, and transport dollies excel and where their limitations lie, and what you need to consider when selecting qualified operators.
Why the Delivery of Machinery Determines the Project Deadline
Machinery installation refers to the entire journey of a machine or plant component from the transport vehicle to its final installation site. This includes unloading, transporting the machine through gates and buildings, lifting it to upper floors if necessary, and finally positioning it precisely on the foundation or at the prepared connection points. Unlike machine relocation—in which an existing system is dismantled, moved, and reassembled—this process focuses on the path of a delivered component into the building.
In large-scale projects, equipment delivery is usually on the critical path. As long as a piece of equipment is not in place, the electrical, utility, and piping trades cannot connect to it, and any delay pushes back installation and commissioning. If the correct equipment is missing on the installation day, this results in wait times for personnel and vehicles, reorders with lead times, and—in the worst-case scenario—a delivery window that must be renegotiated. Transporting machinery within the plant is therefore not a minor aspect of logistics, but a planning component in its own right.
What Information You Need to Know Before Choosing a Device
Choosing the right equipment depends on a few key pieces of information. The sooner this information is available, the more accurately the installation can be planned, and the less often it will be necessary to improvise on the job site.
Load data, center of gravity, and attachment points
The total weight alone is not sufficient for planning. The location of the center of gravity is just as important, because many machines have an uneven structure, and an off-center center of gravity significantly alters the load distribution on forks, crane hooks, or air cushions. In addition, the dimensions—including packaging and transport securing—as well as the slinging and lifting points specified by the manufacturer must be considered. For equipment from abroad, it is advisable to request this information early on and verify its plausibility, as documentation is not always complete.
Soil Conditions and Bearing Capacity
Each method of transporting equipment places a different load on the subfloor. A forklift transfers its own weight and the load to the floor as a high point load through a few wheels; a transport cart does so through its rollers; while an air cushion system distributes the load over a large area. Key factors include the permissible surface and point loads of the warehouse floor, the condition of covers, ducts, and shafts along the transport route, and the surface itself. If you do not know the floor specifications, you should clarify them with the building owner or a structural engineer before planning.
Access Routes and Entry Openings
The route to the installation site is often the real bottleneck. Gate widths and clearance heights, columns, ramps, tight turns between existing structures, and the clear height beneath crane tracks or ventilation ducts determine which units are even viable options. If a component needs to be installed on an upper floor, an access opening in the facade or ceiling is required, as well as a landing area for the crane that can safely support its load. Ongoing operations in adjacent areas and other trades working simultaneously must also be taken into account, as they dictate time windows and restricted access areas.
Air Cushions, Forklifts, or Loading Cranes: A Comparison of the Equipment
No single device can handle every situation. The most common delivery methods differ primarily in terms of the phase of delivery in which they are most effective and the requirements they place on the load and the environment.
Truck with a Loading Crane: Transport and Lifting in a Single Vehicle
A truck equipped with a loading crane combines delivery and lifting functions. It transports components to the construction site, unloads them on its own, and can lift them over obstacles onto platforms, stages, or into access openings. This eliminates the need for a separate mobile crane—including its own travel and setup time—in many applications. High-performance Fassi F1450R-HXP loading cranes achieve a maximum load moment of 119 metric tons-meters and a hydraulic reach of up to 31.80 meters with the jib.
The key factor here is the logic of the load moment: The further the crane boom extends, the lower the permissible load on the hook. Therefore, the planning process is not based on the maximum lifting capacity, but rather on the crane’s load chart for the specific outreach. The crane’s location is equally critical. The outriggers transfer high forces into the ground, which is why bearing capacity, distance from pits and slopes, and sufficiently large outrigger pads must be determined in advance.
Forklifts and telescopic handlers for loads up to 35 metric tons
Forklifts are a type of industrial truck and are the standard equipment used for unloading and horizontal transport on paved surfaces. Heavy-duty forklifts with load capacities of up to 16 metric tons are used to move machinery into place; for particularly heavy components, equipment with capacities of up to 35 metric tons is also used. However, the rated load capacity applies only to a specific distance from the center of gravity. If a machine’s center of gravity is farther from the forks, the actual usable load capacity decreases significantly. It is also important to note the high axle load of heavy-duty forklifts, which places significant stress on floor slabs, manhole covers, and ramps.
Telescopic handlers complement forklifts when height and reach are required, such as when placing loads on platforms or over obstacles. Here, too, the permissible load varies with the extension length and lift height, so the load chart for the specific machine serves as the basis for planning.
Air-cushion transport systems for delicate floors
Air-cushion transport systems operate on a simple principle: Compressed air flows into flat cushion elements beneath the load, forming a thin film of air between the cushions and the floor. This reduces friction so significantly that loads weighing several metric tons can be moved with minimal force and shifted in any direction. Systems designed for loads of up to 36 metric tons are particularly well-suited for narrow warehouses, for maneuvering between existing equipment, and for precise final positioning, because the machine can rotate in place and move sideways.
Since the load is distributed over a large area, only minimal localized ground pressure is exerted, which protects sensitive or coated floors. The limitations lie in the floor’s condition: joints, cracks, floor grates, or porous surfaces allow air to escape and prevent a uniform air film from forming. Such areas can often be bridged with cover plates, but they must be identified in advance. Slopes and inclines are critical because the load has little traction on the air film and must be guided safely. In addition, the system requires a sufficient supply of compressed air, which can be provided by a portable compressor if necessary.
Heavy-duty transport carriages for rugged surfaces
Heavy-duty transport dollies are rolling platforms that are slid under a lifted load. Typically, the machine is lifted using hydraulic jacks, the dollies are positioned underneath, and the load is then moved along them, guided by a steerable dolly at the front. Casters for loads up to 12 metric tons are quick to set up and less sensitive to joints and minor unevenness than air cushions. On the other hand, they concentrate the load on just a few rollers, so the floor’s allowable point load must be checked with particular care.
Once the equipment has been delivered, installation begins, and this is where aerial work platforms come into play. With working heights of up to 28 meters, they enable the safe connection of cable trays, utility lines, or exhaust systems to the installed equipment. For this reason, they are included in the construction site’s equipment plan from the very beginning.
Why Large Installations Combine Multiple Devices
In practice, a complex machine installation rarely requires just a single piece of equipment. Often, a loading crane or heavy-duty forklift unloads the component at the gate; transport trolleys or air cushions handle the journey through the facility; and a crane lifts individual assemblies to upper levels. It is crucial that the handoffs between these steps are planned: Where will the load be set down, how will it be lifted for the next piece of equipment, and who will coordinate the process on site?
Projects in battery cell manufacturing and the automotive industry in Germany demonstrate just how large the scale of these operations can become. In one project, 60 shipping containers were hoisted into place using cranes and lifting equipment, reaching heights of up to three stories. In another project, up to 2,500 shipping containers, each weighing up to 15 metric tons, had to be unloaded, which required lifting equipment that was reliably available throughout the entire delivery phase. In the construction of a production facility, the challenge was to lift loads weighing 4 metric tons to a height of 25 meters. What these operations have in common is that equipment, personnel, and the schedule were planned as a single unit rather than as individual rental items.
Who is authorized to operate the equipment on the construction site
Having the right equipment alone does not guarantee safe machine installation. It is equally important that only qualified and authorized personnel operate cranes, forklifts, and aerial work platforms. The foundation for this is a risk assessment for the specific operation, which serves as the basis for training, establishing restricted areas, and communication between the operator, the rigger, and the signaler.
Written Authorization in Accordance with BetrSichV and TRBS 1116
The Industrial Safety Regulation requires that employees receive instruction before using work equipment. For work equipment posing specific hazards, the Technical Rule for Industrial Safety (TRBS) 1116 goes a step further and requires a written authorization. These include, among others, cranes, telescopic forklifts, and aerial work platforms. Before authorizing a person to operate such equipment, the employer must ensure that the individual possesses the necessary competencies.
Crane Operator’s License and Certificates of Competency
DGUV Regulation 52 specifies the requirements for cranes. For mobile power-driven cranes, which also include loading cranes, the crane operator must be formally authorized in writing. Training in accordance with DGUV Principle 309-003 is considered proof of qualification. For forklifts, telescopic forklifts, and aerial work platforms, there are separate DGUV principles with guidelines on training and authorization.
In practice, this means: If rented equipment is operated by the client’s own staff, the responsibility for qualification, training, and authorization lies with the company using the equipment. If the service provider supplies trained operating personnel, this burden is largely eliminated for the client. However, coordinating barriers, time windows, and interfaces with other trades remains a shared responsibility.
Machine Installation with HDAO GIGA Technology: Equipment and Expertise from a Single Source
For individual projects, purchasing heavy-duty equipment is rarely worthwhile. In addition to the initial purchase cost, there are expenses for maintenance, periodic inspections, storage, and staff training—even when the equipment is not in use. Renting equipment alone reduces these costs but shifts the responsibility for planning, operation, and coordination to the client. It is therefore often more cost-effective to combine equipment and expertise so that the equipment’s deployment is precisely scheduled to fit the project timeline.
HDAO GIGA Technology supports large-scale industrial projects as a service provider for electrical and mechanical installations and supplies the appropriate equipment for these projects: from trucks with loading cranes to heavy-duty forklifts and telescopic handlers, as well as air-cushion transport systems, transport trolleys, work platforms, and complete construction site infrastructure. Our services page on machinery relocation demonstrates how we move existing equipment to a new location. Our industrial assembly team handles the connection work after delivery, while our project and construction management team coordinates all trades. If the delivered equipment originates from China, read our article on CE conformity for Chinese equipment to learn about the requirements that must be met before commissioning.
This article provides a general overview and is not a substitute for safety or legal advice in specific cases.
Frequently Asked Questions About Machine Installation
What type of floor is suitable for air-cushion transport systems?
The ideal surface is smooth, level, and as dense as possible—such as sealed concrete or an industrial coating. Joints, cracks, and floor grates allow air to escape and should be covered with cover plates before transport.
What is the maximum weight a load can be for an air cushion?
That depends on the number and size of the cushion elements. HDAO GIGA Technology uses air cushions for loads of up to 36 metric tons. The key is to distribute the load evenly across the individual cushions.
Do you need a crane operator’s license to operate a truck-mounted loading crane?
Loading cranes are considered mobile, power-driven cranes. The crane operator must be formally authorized in writing and must demonstrate his or her qualifications, typically through training in accordance with DGUV Guideline 309-003.
What is the difference between machine installation and machine relocation?
Machine installation refers to the process of moving a delivered machine from the transport vehicle to its final location. Machine relocation involves dismantling an existing system, moving it to a new location, and reassembling it there. Installation is often a step in the relocation process.
How far in advance should the installation of a machine be planned?
As soon as the load data and delivery time are confirmed—ideally several weeks before the delivery date. This allows enough time for an on-site inventory, soil testing, equipment scheduling, and coordination with other trades.