Installation and Commissioning of Cell and Module Assembly Lines in Poland
As a general contractor for electrical automation. Pre-assembly off-site. Support extending beyond the commissioning phase. We assembled and commissioned the assembly lines for a battery production facility at a site in Poland and supported the client through to the start of ongoing production.
GU
for electrical automation
Poland
Location of Execution
Pre-assembly
Off-site Prefabrication
Start-up
Support After Commissioning
The Initial Situation
Cell and pack assembly lines for battery production were built at a Polish site. Electrical automation was a separate, integrated component of the overall project, and a manager was sought to oversee this part as a general contractor. The requirement was not the execution of individual trades, but rather responsibility spanning from pre-assembly through installation to commissioning.
Assembly lines for cells and packs consist of many similar stations, and that is precisely what makes them prone to delays. Any delay at one station is repeated throughout the line. In addition, construction time is the most critical factor in an ongoing plant build, while the true test comes only after commissioning. A line that has been accepted does not necessarily produce consistently yet. The client needed a partner who could cover both aspects: the assembly and the period that follows.
Assembly lines for cells and packs consist of many similar stations, and that is precisely what makes them prone to delays. Any delay at one station is repeated throughout the line. In addition, construction time is the most critical factor in an ongoing plant build, while the true test comes only after commissioning. A line that has been accepted does not necessarily produce consistently yet. The client needed a partner who could cover both aspects: the assembly and the period that follows.
What We Have Taken On
As the general contractor, we were responsible for the electrical automation, from pre-assembly through to the start of production:
- GU Function for Electrical Automation
- Project Management and Construction Management
- Mechanical and Electrical Pre-assembly
- On-site mechanical and electrical installation
- Software Development for Cell and Pack Assembly Lines
- Commissioning
- Production Support After the Start-up
A person responsible for the entire scope of automation, from prefabrication in the workshop to the production line operating on a cyclical basis.
Pre-assembly at the construction site
Mechanical and electrical assemblies were pre-assembled before being delivered to the construction site. In the workshop, work can be carried out under better conditions and without having to worry about other trades, and errors are caught where they can be corrected at minimal cost. This meant that only assembly took place on site, not manufacturing. This reduces the time spent on the site, which is the most expensive part of an ongoing factory construction project.
Project Management and Construction Management Under One Responsibility
For the electrical automation, we served as the general contractor, including project management and construction supervision. This meant that the scope was not coordinated by an outside party but was managed by the same entity that carried it out. As a result, for the overall project, the automation team served as a single point of contact rather than a collection of individual trades.
From Commissioning to Stable Production
After commissioning, we continued to support the production ramp-up. During this phase, assembly lines often reveal their limitations under continuous operation, and these issues can be resolved more quickly when the on-site technicians are the ones who set up the equipment themselves. The client did not have to begin the ramp-up process with a new partner.
What Made This Project Special
The critical point in such projects is not the assembly itself, but rather the two end stages. Up front, prefabrication determines how much time the construction site will take. Down the line, the startup phase determines whether an accepted line actually goes into production. Both of these stages are typically outside the scope of the assembly contract, which means there is no one responsible precisely where delays occur.
As the general contractor, we were responsible for the electrical automation—including project management and construction supervision—from pre-assembly through installation and commissioning all the way to the production ramp-up. For the client, this meant having a single point of contact throughout the entire process, rather than having to contract out prefabrication, installation, and ramp-up support separately.
As the general contractor, we were responsible for the electrical automation—including project management and construction supervision—from pre-assembly through installation and commissioning all the way to the production ramp-up. For the client, this meant having a single point of contact throughout the entire process, rather than having to contract out prefabrication, installation, and ramp-up support separately.
Project Data
- Role: General Contractor for Electrical Automation
- Location: Poland
- Management: Project Management and Construction Management
- Prefabrication: mechanical and electrical pre-assembly
- Scope of Work: Mechanical and Electrical Installation
- Software: Development for Cell and Pack Assembly Lines
- Final Phase: Commissioning and Production Support
Do you need installation and commissioning services from a single provider?
Whether it’s pre-assembly, on-site installation, commissioning, or support during the production ramp-up, we handle the entire scope as a general contractor and remain on site until the plant is running at full capacity.