Electrical Installation of a Production Line in China
Eight months from planning to a fully operational line. Carried out in China. Integrated with the overarching control system. We were responsible for all electrical engineering work on a transmission logistics line, from electrical design and control panel construction to on-site commissioning.
8 months
Implementation Period
China
Location of Execution
Wayfinding System
Integration with Production Management
Everything
all in one place
The Initial Situation
An automaker had a transmission logistics line built at a Chinese facility. For the electrical engineering, the company sought a partner who would not handle the project in piecemeal fashion, but would manage the entire process—from electrical design and the manufacture of switchgear and software all the way through to commissioning. The deadline was set from the very beginning: eight months from planning to a fully operational line.
In Europe, adjustments to a project of this scope can be made quickly due to short distances. In China, it’s different. If something is wrong in the planning phase, it isn’t noticed in the office but on a construction site several hours away by plane, and every correction there takes more time than one that is resolved beforehand. Added to this was the integration with a higher-level control system, whose requirements were specified from outside the project. The line had to be up and running in eight months—at a location where coordination is more expensive than preparation.
In Europe, adjustments to a project of this scope can be made quickly due to short distances. In China, it’s different. If something is wrong in the planning phase, it isn’t noticed in the office but on a construction site several hours away by plane, and every correction there takes more time than one that is resolved beforehand. Added to this was the integration with a higher-level control system, whose requirements were specified from outside the project. The line had to be up and running in eight months—at a location where coordination is more expensive than preparation.
What We Have Taken On
We were fully responsible for the electrical engineering of the line, from design through commissioning:
- Comprehensive Electrical Engineering Services Under One Roof
- Electrical Design of the Line
- Control Panel Construction
- Software Development
- HMI Visualization
- Electrical Installation at the Chinese Site
- Integration with the higher-level control system
- Commissioning
- Completed in eight months
A single point of contact for all electrical engineering needs, bridging the gap between planning and the construction site.
Electrical Engineering: From Planning to Commissioning
Electrical design, control panel fabrication, software, and HMI visualization were all under one roof. For a project of this scope, that’s not a convenience—it’s a matter of meeting deadlines. When design and manufacturing are handled in-house, changes are implemented rather than negotiated. The switchgear could be prepared while the design phase was still underway, and by the time installation began on-site, the electrical configuration had already been finalized.
Processing at the Chinese facility
The electrical installation and commissioning took place in China. We have been working between the European and Asian markets for years and know which details need to be clarified before arrival and which can be resolved on site. As a result, the process remained the same for the client as it would have been for a project in Europe, without the need for the client to organize anything on site.
Integration with the higher-level control system
The line had to transfer its data to a higher-level control system whose requirements were not part of its own scope. We implemented the integration and verified that it met the specifications before commissioning began. As a result, the line was not only operational at startup but also visible in the production management system.
What Made This Project Special
Eight months is a tight schedule for a project, from electrical design to commissioning, and the time becomes even tighter over such a distance. Each step depends on the one before it. The switchgear depends on the design, the software on the hardware, and commissioning on everything that came before. On a construction site in Europe, a one-week delay in the schedule can be absorbed. In China, that translates to one more trip.
We were responsible for the entire electrical engineering project, from planning and manufacturing the switchgear to commissioning and connecting to the control system. For the client, this meant having a single point of contact for the entire scope of electrical engineering work—at a location where every additional interface is more expensive than in Europe.
We were responsible for the entire electrical engineering project, from planning and manufacturing the switchgear to commissioning and connecting to the control system. For the client, this meant having a single point of contact for the entire scope of electrical engineering work—at a location where every additional interface is more expensive than in Europe.
Project Data
- Scope: Overall scope of electrical engineering work
- Location: China
- Planning: Electrical Design of the Line
- Manufacturing: Control Panel Construction
- Software: Software Development and HMI Visualization
- Scope of Work: Electrical Installation and Commissioning
- System Integration: Higher-Level Control System
- Project duration: 8 months
Are you planning a project in Asia?
Whether it’s electrical design, switchgear construction, on-site installation, or integration into a higher-level system, we handle all electrical engineering needs between the European and Asian markets, with a single point of contact for both sides.