Commissioning of a Battery Cell Manufacturing Facility as a General Contractor
As a general contractor. Electrical and mechanical hook-up from a single source. Planned using a 3D model. We installed, positioned, and prepared the plant engineering for a new battery cell production facility for connection, including work in the cleanroom and dry room areas.
GU
Overall Responsibility
6
Bundled Services on a Contract Basis
3D BIM
Planning and Clash Detection
Clean & Dry Room
Runtime Environment
The Initial Situation
A battery cell manufacturer set up a new production facility. The equipment was supplied by several international vendors, each of whose scope of supply ended at the machine itself. This created a gap in the contract between delivery and a fully operational line—a gap that no single vendor could fill. The company was looking for a partner who would take on the entire electrical and mechanical hook-up as a general contractor and coordinate the various trades involved.
Cell-based manufacturing is less forgiving than a traditional production facility. Parts of the plant equipment are located in cleanroom and dryroom areas, where access, material flow, and cleanliness requirements dictate the workflow. At the same time, the schedules of several equipment suppliers were interlinked, while the available construction space remained limited. If one trades starts too early, it blocks the next trade; if it starts too late, it misses its installation window. The equipment had to be installed in the correct order and be ready for connection without the trades hindering each other.
What We Have Taken On
We carried out the project as the general contractor and managed the entire hook-up as a one-stop solution:
- Overall Project as General Contractor
- Electrical Hookup of the Production Lines
- Mechanical Hookup of Plant Equipment
- Installation and Positioning of the Capacitors
- Internal Logistics and Machine Installation
- Working in Clean Room and Dry Room Areas
- Construction Site Management Throughout the Entire Project Duration
- BIM Design with 3D Coordination in Revizto
A single point of contact for planning, delivery, installation, and coordination—from the first machine delivered to the line ready for connection.
Electrical and Mechanical Hook-up from a Single Source
Both trades fell under a single area of responsibility, rather than being divided between two contractors. This included the electrical connection of the production lines, the mechanical assembly of the plant equipment, and the installation and positioning of the capacitors. Electrical and mechanical work converge on the same component, and that is precisely where coordination issues between two contractors typically arise. Rather than individual trade services, complete production lines were handed over.
Integration in sync with the equipment suppliers
Internal logistics and the installation of machinery followed a sequence based on delivery schedules and the available construction space at any given time. We planned the transport routes, temporary storage, and installation windows ourselves and coordinated them continuously with the suppliers. If a delivery was delayed, the sequence was adjusted, but not the deadline. This ensured that no machine was left sitting unnecessarily on the site waiting for its designated spot.
Design for use in cleanroom and dryroom environments
Part of the installation took place in areas with specific cleanliness and humidity requirements. Personnel, tool selection, and material flow were tailored to these requirements, and protective measures were in place throughout the entire installation period. For the equipment suppliers, this meant they were able to install their systems in an area where approval following our installation was never in question.
What Made This Project Special
The real challenge lay in the density of the interfaces. Equipment from multiple suppliers, utility routing, electrical installations, and conveyor systems all occupy the same space, and a clash is significantly more costly on the construction site than it is in the model. We therefore planned the implementation using a BIM model and integrated the models from the equipment suppliers into Revizto. Conflicts were resolved before installation began, rather than after they were discovered.
As the general contractor, we were responsible for the hook-up—from planning through installation to a system ready for connection—including the coordination of all trades involved. For the client, this meant having a single point of contact for the entire hook-up process, rather than having to coordinate numerous trades individually.
Project Data
- Role: General Contractor
- Work Scope: Electrical and Mechanical Hook-up
- Installation: Internal Logistics and Machine Installation
- Special Scope: Installation and Positioning of the Capacitors
- Environment: Cleanroom and dry room areas
- Planning: BIM with 3D Coordination in Revizto
- Construction Supervision: End-to-End Construction Site Management
Are you planning a hookup?
Whether it involves electrical and mechanical hook-up, installation of plant equipment, or assembly in cleanroom and dryroom areas, we handle the entire scope of work as a general contractor, with a single point of contact for all trades involved.